Bournemouth Beach top-ups 2008-2010

Legacy Council archive project

BIS4.3 March 2008 at Southbourne, the dredger Oranje on the horizon

Bournemouth Beach Improvement Schemes (BIS) 4.3, 4.4 and 4.5.

During the three years 2008-2010 the council pledged to make good annual losses of material to keep the beach at a constant level and volume between Boscombe and Southbourne. Renourishment was localised and took just a few days.

BIS4.3 – March 2008

A project to renourish a small section of beach between Boscombe & Southbourne. The dredger Oranje delivered sand to the coast between 8th-14th March 2008.

A section of beach between Boscombe and Southbourne was renourished this winter by the Fareham-based Westminster Dredging Company and the Dutch dredger Oranje. The sinkerline was positioned on the beach just west of Groyne 30 (Portman Ravine) between Boscombe and Southbourne. From there four groyne bays were renourished, working east to Groyne 32 (500m), and west to Groyne 28 (300m). Groyne numbers are indicated along the promenade.

Beach material was dredged off the Isle of Wight and brought by the dredger close to the beach at Groyne 30. The dredge/sail/discharge cycle from the IOW took approximately 11 hours.

The project suffered bad-weather delays. Originally projected to take just 3 days, the eight hopper loads of sandy beach material were delivered to the beach over a period of one week.

BIS4.4 – March 2009

A project to renourish a small section of beach at Southbourne. The dredger Crestway delivered sand to the coast between 4th-21st March 2009.

Undertaken by Fareham-based Westminster Dredging Company, using the Dutch dredger Crestway. Crestway made her first delivery to the beach on Wednesday 4th March 2009.

Beach material was dredged off the Isle of Wight and brought close to the beach by the dredger from where it was pumped ashore through a 300m long floating pipeline and then levelled by bulldozers. The dredge/sail/discharge cycle from the IOW took approximately 11 hours.

BIS4.4 was completed on Saturday 21st March, with 74,192m³ added to the beach between Groynes 50 & 53.

Three groyne bays were replenished between Groynes 50 & 53 at Southbourne.

Further work – the existing timber groynes 51 and 52 are life expired and will shortly be rebuilt, using the renourished beach as a working platform.

BIS4.5 – September 2010

A project to renourish a section of beach at Southbourne between Portman Ravine Groyne 28 and Fisherman’s Walk Groyne 32. The third and final of the Bournemouth beach top-ups.

Work began on 12th September 2010 on the beach top-up of a section of beach at Southbourne by the Fareham-based Westminster Dredging Company.  

The pumping of approximately 70,000m³ of beach material was completed on 20th September and the beach fully reopened to the public 10 days later.

Four groyne bays were renourished between Groynes 28 & 32 at Southbourne.