New flood defence structures for Creekmoor and Sterte Channels, housing tidal valves to prevent tidal water travelling back up the channels during high tides.
Lead Authority
BCP Council
Working with
Project start date
26 March 2018
Project completed
23 July 2018
The Creekmoor Channel
The Creekmoor Channel
The Sterte Channel
Project Overview
New flood defence structures have been constructed at the end of the Creekmoor and Sterte Channels where they meet Holes Bay. The structures house tidal valves which will prevent tidal water travelling back up the channels during high tides. Ground levels around the structures have also be raised using recycled soil to continue the line of flood defences in these areas.
- The works at Creekmoor started early April 2018 and were completed, to schedule, on 30th May.
- The works at Sterte followed the Creekmoor project, starting on 30th May and completed, also to schedule, on 23rd July.
- Progress reports & flood defence design information can be found below.
Poole Council worked with the Environment Agency and Wessex Water to secure funding of some £700,000 to deliver these flood defences. The work was carried out on behalf of Poole Council by Avon Construction Ltd.
Creekmoor channel project
The structure across the mouth of the channel is constructed from two rows of sheet piles driven into the seabed and filled with concrete.
The flood defence structure here forms a bridge with foot/cycle way across the channel, an improvement on the previous route that took pedestrians & cyclists via a ‘dog-leg’ close to the busy Upton Bypass.
Please click on an image to open the gallery for a description of each photograph
A ‘fish friendly valve’ is included in the Creekmoor structure to ensure eels are not restricted in their migratory movement through the surface water system from Holes Bay to waterbodies upstream, e.g. Creekmoor & Millfield ponds. There is no evidence to suggest fish or eels use Sterte channel. This is because it has a concrete base and sheet pile walls, as well as a pumping station which restricts any movements upstream.
Sterte channel project
The structure across the mouth of the channel is constructed from two rows of sheet piles placed on to the existing concrete base, and filled with concrete.
Please click on an image to open the gallery for a description of each photograph
Why is the work needed?
It has been recognised that parts of Poole are likely to face a higher risk of flooding due to sea level rise in combination with a more frequent occurrence of wet and stormy weather. This project is one of the defence measures identified to help minimise the flood risk.
References
- Adapting to Climate Change – Advice for Flood and Coastal Erosion Risk Management Authorities, April 2016: www.gov.uk/government/publications/adapting-to-climate-change-for-risk-management-authorities
- UK Climate Projections 2009: ukclimateprojections.metoffice.gov.uk/21684