Beach Renourishment 2005-2007, Phase II

Legacy Council archive project

Bournemouth beach renourishment, winter 2006/07

Phase 2 of a 2-year project to renourish the beaches of Poole Bay

During the first phase of this 2005-2007 project (Phase I) some 1.1 million m³ of material was used at beaches at Swanage, Poole & Bournemouth (Hengistbury Head to Southbourne). For Bournemouth this was Beach Improvement Scheme (BIS) 4.1.

This second phase of the project continued along Bournemouth beach during the winter of 2006/2007 (BIS4.2), between Boscombe and Alum Chine, using a further 900,000 m³ of sand from a Licensed Dredging Area off the Isle of Wight.

Bournemouth beach has been renourished on four previous occasions in the last 36 years and is now effectively an artificial beach.

Work was carried out by the Fareham-based Westminster Dredging Company with the Dutch dredger “Oranje”. The project team arrived w/c 6th November 2006 to undertake hydrographic and side scan sonar surveys of the sea bed. The Oranje arrived on 13th December.

The beach was first renourished east towards Boscombe Pier & Southbourne. Work continued west to Bournemouth Pier and on to Alum Chine. The project was completed on 23rd January 2007.

Availability of sand

For Phase 1 of this project material dredged during a Poole Harbour deepening project was used for beach renourishment, but the quantity of sand available was insufficient to complete the entire beach at Bournemouth. Work continued during winter 2006/07 (BIS4.2) using material purchased and transported from a Licensed Dredging Area to the east of the Isle of Wight.

Further work at Bournemouth

Bournemouth’s existing timber groynes will last another 8 years or so, after which consideration will be given as to what should replace them.

In the past Bournemouth beach has been renourished at intervals of 15 years or so, by which time most of the sand has been lost. For the next 3 years small scale top-ups will be used to maintain beach width and volume.

The ongoing need for beach renourishment

The standard of flood and coast protection at Poole Bay depends mainly on the level and width of its beaches. Construction of seawalls and promenades over the course of the last century (1907-1970) put a stop to the natural supply of beach material from cliff erosion and it is necessary to occasionally replace beach material lost to longshore transport to the east, driven by wind and waves.

In the 30 years between 1970-2000 almost 2 million m³ of sand was used to replenish the beaches at Bournemouth and Poole. The on-going need for beach renourishment was identified in the Poole and Christchurch Bays Shoreline Management Plan 1999, and a subsequent report by Halcrow (2004) suggests that a further 3 million m³ will be required over the next 50 years in order to maintain protective beach levels and widths.