Poole Bridge to Hunger Hill Flood Defence Scheme 2025-2027

New infrastructure is being constructed to reduce tidal flood risk in Poole town centre, the Old Town and surrounding areas over the next 100 years. Sea wall heights will be raised at intervals to keep pace with rising sea levels.

Lead Authority

BCP Council

Working with

Budget

£29.4 million

Project start date

Autumn 2018

Last Updated

14 July 2026

Overview

Poole Bridge to Hunger Hill is the last remaining undefended waterfront in the town centre. There is a high and present day risk of tidal flooding which increases significantly over the next century due to climate change and sea level rise. BCP Council, in collaboration with the Environment Agency, landowners, developers and other relevant organisations, is working to provide a continuous flood defence (delivered in phases) along 1.5 km of the eastern side of Holes Bay (see the area map above).

Holes Bay Path to Lifeboat Quay (Zone A)

From June – October 2026

The flood defence scheme will blend in with high ground at both ends of Zone A, near Sterte Avenue West on the A350 and at the Aqua Apartments on Lifeboat Quay. The current levels along the Holes Bay path are typically 1.8m Above Ordnance Datum (AOD) (about AOD). The required standard for flood defence purposes is 2.65m AOD. The path will be raised and widened, and the rock revetment will be upgraded. At certain pinch points (where the path cannot be raised), sheet piles will be installed adjacent to the rock revetment. Surface water from the new path will be directed to the grassed area. The raised path will gradually slope down to the existing pedestrian crossings on Holes Bay Road and Lifeboat Quay.

Along Lifeboat Quay, the new defences will run parallel to the road rather than on the water’s edge. This avoids SSEN’s high voltage electricity cables which supply Poole. Two flood gates will be installed – one on the corner of Asda’s water side path and one at the existing zebra crossing. Both gates will be closed when risk of flooding is high, and they allow easy access during normal conditions.

Works in Zone A are expected to take around five months, subject to weather conditions. Thank you for your patience during the construction of these essential flood defences.                                                                                

Sheet piling works – Zone A

The installation of steel sheet piles will take place from the land. We anticipate that the piling works along the Holes Bay path will take approx. four weeks and around Lifeboat Quay Road approx. two weeks, subject to ground conditions. Noise generated from the piling will be in short duration only. Any noise and vibrations are monitored, as per planning conditions to ensure they remain within approved tolerance levels.

Piling Update – 22 July 26:  Piling of the longest 9m sheet piles along Holes Bay path is complete. The continuation of shorter-pile driving will start along Lifeboat Quay, from later today. It will begin next to the Aqua Apartments and move towards the A350. Acoustic barriers will be used with the piling equipment to help minimise noise disturbance. Any noise created comes from the sheets reverberating when they hit solid ground, rather than being caused by the machines and the piling method being used.  We apologise for any inconvenience this may cause.

Traffic management – A350

From 01 June, a temporary lane closure and speed limit reduction from 40mph to 30mph was introduced on the northbound highway of the A350, from Lifeboat Quay to around Sterte Avenue West.

Off-peak lane closures will take place from between 09:00 – 15:30, as required. 

Bus Stop – temporary re-location

From 08 June, the bus stop on the corner of Lifeboat Quay and the A350 was relocated southwards, near Costa Coffee. Directional signage is provided to ensure minimum disruption to journeys.

Holes Bay path – temporary pedestrian and cyclist diversion route from 01 June

The Holes Bay Path is temporarily closed to all users. It is an active construction zone with heavy machinery operating in the area to install sheet piles and upgrade the rock revetment. The original path tarmac surface has been removed; when the path is re-instated, sections of it will be raised and widened.

The safe diversion route is via Sterte Green, please follow the on-site diversion signs. Thank you.

RNLI car park to Poole Bridge (Zone E)

Works due to commence Autumn 2027

As works get underway on Zone A, the construction detail from the contractor is being finalised. Defence heights in this area will increase from approximately 1.2m to 3.6m AOD. They will comprise a steel tubular and sheet-piled wall with flood gates where access is required. With most of this frontage subject to future regeneration plans, ground levels are intended to be raised to the same height of 3.6m AOD to establish a traditional quay wall, as regeneration takes place.

Holes Bay is a highly protected area due to the presence of migratory birds, breeding fish, and seahorses. These factors, with the complex mix of private infrastructure and assets, combine to restrict when and how works can be undertaken. We continue to work with all land interests directly impacted by the scheme to progress agreements prior to construction. The final phase of these essential flood defences has been re-scheduled for construction in Autumn 2027.

Ground raising at Slip Way (Zone C)

Works completed July 2025

The highway around the harbour access point between the RNLI buildings (Lifeboat Quay Slip Way) was raised to 2.49m AOD to reduce flood risk for the next 50 years. New marine vessel storage racks have been installed to accommodate the modified flood defence height.

Works were carried out May-July 2025; our thanks to the RNLI and Poole Harbour Association for working closely with us to keep disruption to a minimum. Works to the highway did not require planning permission.

Flood defence scheme explainer video

Pre-project preparations

Compound site set-up and vegetation clearance, August 2025

Site set-up took place through August. In preparation for the construction works vegetation clearance was carried out at Lifeboat Quay involving the removal of several trees and self-seeded plants to make room for the new flood defences. Following construction, new low maintenance coastal planting will be introduced. At the compound site, grass has been removed to create a safe hard standing for cabins and construction vehicles and equipment. It will be re-instated when the flood defence work is finished.

Planning approval, July 2025

Consent to build the new flood defence infrastructure along Zones A and E was granted on 18 July 2025 – ref APP/24/01215/F (the application details will be displayed once you agree to the disclaimer notice on the BCP planning portal)

Proud to support Outdoor Classroom Day, May 2025

The Poole Bridge to Hunger Hill project team including South West Flood & Coastal, Dalcour Maclaren and Knights Brown celebrated our coast by welcoming over 166 enthusiastic pupils from seven local schools to this special day at Baiter Park, Poole.

The event was led by Dorset Coast Forum. Outdoor Classroom Day is a global movement to inspire outdoor play and learning.

Read More

Public Consultation, September 2024

During our consultation period, we asked for views on the impacts of the proposed scheme and how we might minimise any disruption during construction.

  • BCP residents were invited to complete an online survey (or a paper version available in all BCP libraries). Meetings with directly affected stakeholders continued during this time. An Information Document was provided to help everyone understand our proposals.
  • We held a drop-in event on Thurs 5 September (10am – 4.30pm) at Scouts Hall West Quay Road, Poole. Thanks to all of those who turned out in the rain to read our display panels and talk to the team.
  • We also held an online presentation and Q&A session on Wed 11 September (6.45 – 8.00pm). If you missed it, a video recording is still available to view at YouTube.

Feedback from our public consultation (Have Your Say | BCP Council) and stakeholder meetings was analysed during in October. Based on community feedback, adjustments were made to the design, including the incorporation of additional flood gates to maintain access for businesses and the public, and modifications to the landscaping plan to enhance the visual appeal of the flood defences” – for more information please see the Statement of Community Involvement (section 4.3) and how it informed the Planning Application submitted in November 2024. Stakeholder meetings will continue throughout planning and construction.

Flood risk in Poole

The Poole Harbour and Wareham, Flood and Coastal Erosion Risk Management Strategy (2014) identified that within Central Poole there are 573 properties at high flood risk in the present day, rising to over 2,000 properties at flood risk by 2110. In recognition that regeneration was not forthcoming to provide the flood defences, we tabled the option of a Council-led scheme and it gained outline business case approval by BCP Cabinet in September 2020. Initial funding from the Environment Agency was awarded to the proposed scheme in January 2021 [more]. 

The land along Back Water Channel is in a mixture of different private ownerships. The current quay walls simply retain the earth and are not considered to be flood defence infrastructure. Many do not have a crest level higher than the land behind and some require urgent attention.

Scheme benefits

The benefits of a flood defence scheme, delivered in a single phase, include:

  • Mitigating the increasing risk of flooding to people and property, caused by climate change over the next 100 years.
  • Contributing positively to public health and well-being by reducing the mental and emotional stress of flooding; as well as the risk to life.
  • Improving and enhancing the condition or integrity of the local environmentally designated sites and marine habitats.
  • Unlocking land for future redevelopment by private landowners where buildings are expected to provide vibrant ground-floor frontages for businesses and new homes for local people on the upper floors.
  • Creating new public quayside and waterfront routes in Poole Harbour for leisure, exercise and commuter use, positively contributing to the areas sustainability.

Potential costs of flood damage without defences

Without the flood defence scheme, the potential cost of tidal flooding damages to town centre infrastructure and properties, over the next 100 years, could exceed £161 million. This is the area highlighted in red on the Benefits map above. By calculating the cost of damages in a ‘do nothing’ scenario it enables us to bid for central government Grant in Aid funding so that we can do something to reduce the flood risk to local communities. The adjacent area (highlighted orange on the map) shows the area which was used to gain funding for the raising of Poole Quay’s flood defences.

An adaptable design

The scheme is split into five zones, A-E as indicated on our Zones map. Each has different interventions planned for 2026/27, 2071 and 2105 so that sea wall levels keep pace with climate change. BCP Council intends to take ownership and maintenance liability for the new flood defences. This is an important aspect of ensuring we can maintain and adapt it in the future to keep pace with sea level rise.

ZonePresent-day height (mAOD)2020 design (mAOD)2071 proposed (mAOD)
A1.82.653.6
B3.21N/ANew defence by private landowner
C2.22.49 (raised to meet height of Zone D)3.6
D2.49N/ANew defence by private landowner
E1.23.6N/A

mAOD above refers to metres Above Ordnance Datum. Ordnance Datum is the reference point – at Newlyn, Cornwall – from which all heights and elevations are measured in Great Britain for mapping purposes. Newlyn’s sea level is the zero point at 0m, and AOD (Above Ordnance Datum) is anything higher than that point. 

Environmental considerations

The flood defence scheme is in Poole Harbour which has a range of protected special designations including: Ramsar – wetland sites of international importance, Site of Special Scientific Interest (SSSI) and Special Protection Area (SPA). To carry out any work in the Harbour, a number of environmental assessments are required from Natural England, Marine Management Organisation as well as planning consent from BCP Council. Anticipated environmental marine enhancements include benefits for wintering and breeding birds, breeding fish and seahorses & sea sponges.

Funding allocations

The construction cost for the flood defence scheme, delivered in a single phase, is approx. £29.4 million.

The Scheme secured £22.1 million of Flood & Coastal Erosion Risk Grant in Aid from Central Government including:

  • £12.4 million from the Environment Agency in January 2021 (at the Outline Business Case stage*)
  • £3.5 million from Defra in February 2025, when it announced funding for nearly 1,000 UK projects to protect properties most at risk from tidal flooding.
  • £6.2 million from the Environment Agency in additional Grant in Aid funding in June 2025 (following detailed design*)

In June 2025, BCP Council considered the Strategic Prioritisation of Community Infrastructure Levy (CIL) and allocated this principal scheme £7.3 million.

CIL can be used to fund a wide range of infrastructure including transport, flood defences, schools, hospitals, and other health and social care facilities. Under Section 216(2) of the Planning Act 2008 and regulation 59, Local Authorities must spend the levy on infrastructure needed to support development. More info at BCP | Community Infrastructure Levy

* Variation in costs is a normal part of scheme design and delivery, increasing from the initial outline costs to a more accurately costed scheme by the end of the detailed design stage. However, the early estimated costs were subject to very significant increases due to Covid-19 and rapid inflation which greatly impacted the price of concrete and steel. The estimated construction costs were revised to circa £29.4 million at the end of detailed design. Approvals for cost increases were subject to the normal Grant in Aid scrutiny, with the business case still representing good value for money due to the significant flood risk across Poole town centre and unlocking of land for development.

More

Once constructed, this new infrastructure will complete flood defences for Poole town centre, the Old Town and surrounding areas. Other schemes include: